Billing for contractors and interior designers: stages and sign-off
How contractors and interior designers can bill a job in stages, handle extra work and change orders, keep site proof, and collect the final payment after handover.
In this article
The flat is finished, the family has moved in, and the last ₹1,70,000 is stuck on a list of 'small things': a drawer that sticks, a shade of paint, a light that was 'supposed to be' in the passage. For contractors and interior designers, the hardest money to collect is the last instalment, and the reason is almost always a record that was never written down.
Bill by stage, not at the end
A contracting or interiors job runs for weeks or months and you spend on labour and material long before handover. Agree a payment schedule tied to stages of work that both sides can see on site.
Worked example: a 2BHK interior job quoted at ₹8,50,000.
| Stage | What must be visible on site | Share | Amount |
|---|---|---|---|
| Advance | Signed quotation and design drawings | 20% | ₹1,70,000 |
| Civil and false ceiling done | Ceiling, electrical points, plumbing | 30% | ₹2,55,000 |
| Carpentry installed | Wardrobes, kitchen, TV unit fitted | 30% | ₹2,55,000 |
| Handover | Painting, fittings, cleaning, keys | 20% | ₹1,70,000 |
Each stage has a clear test: either the ceiling is up or it is not. Avoid stages like '50% work complete', which nobody can check.
Extra work: the typical dispute
The common argument in this trade is about what was included. The client remembers a loft in the second bedroom; your quotation does not mention it. Or the client asked for an upgrade from laminate to veneer on site, and now does not want to pay the difference.
- 1Make the [quotation](/blog/quotation-vs-proforma-vs-tax-invoice) itemised. Room by room, with sizes and material grade. 'Wardrobe 7 ft × 8 ft, BWR ply, laminate finish' leaves less room for argument than 'wardrobe'.
- 2Write a change note for every change. What changed, the extra cost, and the client's OK on WhatsApp or email, before the work starts.
- 3Bill changes as their own stage or line. For example 'Change 3: veneer upgrade, master bedroom wardrobe, ₹38,000'.
- 4Keep a snag list at handover, agreed with the client, with a date to finish it. Tie the final payment to that list, not to an open-ended 'satisfaction'.
Keep proof from the site
The typical record-keeping problem is that the evidence lives in the site supervisor's phone. When a dispute comes six weeks later, nobody can find the photos.
- Photos at each stage, with the date, before the next trade covers the work. Wiring before the ceiling closes is the classic one.
- Measurement sheets signed or acknowledged by the client.
- Material bills for anything the client is paying for directly or at cost.
- The client's approval of each stage, even a one-line message, kept with that stage's invoice.
Store all of this per job and per stage, so you can send one clear record when a payment is questioned. The article what to do when a customer does not pay explains the next steps if it comes to that.
Common mistakes
- Starting without an advance. Your money is in the client's walls before theirs is in your account.
- Doing changes on a verbal OK. It is forgotten by the time the bill arrives.
- Invoicing two stages together because the first was late. Send each stage's invoice when it is reached.
- Mixing your own purchases with the client's. Record what you bought for each job so your margin on it is clear.
How InvoiceKaro handles staged jobs
Projects in InvoiceKaro holds each job for a saved customer, split into milestones with an amount and due date. You attach proof to a milestone, such as site photos or a signed measurement sheet, mark it delivered, and send the client an approval link. The link records the name they type and the time they approved; it does not verify who they are. Change orders can be added as extra milestones.
Create invoice makes a draft invoice for the milestone without GST: open it, set the GST rate, HSN/SAC and place of supply, then issue it. You can schedule reminders for a milestone (three days before the due date, on it, and 7, 15, 30 and 45 days after), and download an evidence pack with the proof list, reminder log and approval record if a payment stalls. Material bills can be recorded as purchases or expenses, but they are not linked to a project, so keep your own note of which job each bill belongs to. The step-by-step walkthrough is in Projects: milestones, proof and approval.